1. Conceptual Design.
1.1 Gather information required for the design including TOR, site condition, etc. and analyze the information received
1.2 Preliminary design according to a design concept and existing data.
1.3 Prepare documents submitting to Owner or its representative.
2. Detailed Design.
2.1 Work with other FEC department/disciplines for project planning and scheduling
2.2 Data analysis and coordinate with others for further clarification and requirements.
2.3 Perform the desi
1. Design structure of the buildings and prepare project specifications
2. Ensure Owner’s requirements and/or architectural opinion are incorporated into the design
3. Coordinate with designer of each system when necessary.
4. Develop detailed specifications for structural engineering.
5. Perform preliminary cost estimate.
6. Consider timeframe of the construction and assist planning office to develop the project schedule.
7. Look for an opportunity for an improvement of the construction
1. Design structure of the buildings and prepare project specifications
2. Ensure Owner’s requirements and/or architectural opinion are incorporated into the design
3. Coordinate with designer of each system when necessary.
4. Develop detailed specifications for structural engineering.
5. Perform preliminary cost estimate.
6. Consider timeframe of the construction and assist planning office to develop the project schedule.
7. Look for an opportunity for an improvement of the construction