From : January 2007 to JUNE 2007 (Chana Gas Separator Plant)
Company Name : CoGS
Position : Pipeline SAP PROGRAM Technicain
Job Detail: Reading shop Drawing for Construction GIS Pipeline.
Key Data On The Program Sap Pipeline Department
Assistant Save and Install Document Control Program Sap.
From : JULY 2007 to : December 2008
Company Name : Green River Panal (Thailand) Co., Ltd.
Position : Production Technical operator. (Project MDF WOOD Rubber Plant)
Job Detail:
-. Installation Structural assemble equipment Fabrication main and Sub main Machinery In Industrial Rubber wood.
-.Planing and control Work Progress schedule for equipment Installation .
- Check Lube oil Hydraulic After Installation Work and pressure test and flushing of lube oil piping System.
-. Start stop and Commissioning Run Tests Main Machinery In Line Process. Plant.
To Coordinate Install Machinery Mechanical equipment and Assistant Engineering Install Mechanical Machinery .
Defect work and spraypaint lubricate Welding Piping work machinery and electricity and power machinery.
From : January 2009 to December 2009
Company Name : Haad thip company limited. (Project Installation Machinery mechanical and electricity).
Position : machine – Tool Operator and Install Machinery..
Job Detail :
- Installation Machinery mechanical assemble equipment Fabrication And . Start Stop and Run Tests Commissioning Machinery and
equipment After Installation Line Process Coca- Cola Berverage.
Control Operator. Machinery the head packing and Defect work machinery and electricity. Total Line Process Coca- Cola Berverage.
Inspector and Maintannance Machinery Total Line Process Coca- Cola Berverage.
From : January 2010 to November 2010
Company Name : Thai yarnyon Sale and Service Company Limited. .Position : Machanic .
Job Detail : Overheal Maintennance And Repair Engine , gears, lower automobile portion a car brand Europe (Audi , BMW, KIA, Volvo,
Citroen ,Volkswagen,Skoda,Seat,Peugeot.)
Check automobile electricity Moniter Symbol Show a room takes Drive erase the data.
Check Service gum rubber tire wind . automobile boiler . oil Break gears Auto oil . Engine oil . steering wheel oil . Cooling fan
water Check working other.
From : December 2010 to October 2011
Company Name : TATRIBUT ENGINEERRING CO . LTD.
Position: Technical (Project Building. Tesco lotus department store Hatyai )
Job Detail : Installation assemble equipment Fabrication Air conditions , Chilled water , FCU , AHU, DUCT PIPING Work and Motor Pump total Building. Tesco lotus Hatyai department store Project.
- Commissioning run test Equipment Machinery mechanical and Maintenances Basic total After Installation. equipment Total Tesco lotus
Hatyai Project.
- To isolate Fabrication mechanical system and with Maintenance/Engineering unit for isolation of electric and control system to Enable
operator to work safely .
- Inspection Work after Installation And Quality Control
.
From : December 2011 to August 2012
Company Name: SBANG CONSTRUCTION LTD.
Position: Maintennance Technician (Project Songkhla Power Plant Biomass APKG 9.9 )
Job Detail : Maintennance and Rapier Machinery Truck the machinery is heavy total as After build Construction Structure power plant
Biomass APKG 9.9 MW projects.
-tab Responsible for Work Maintenance total for Power Plant Biomass APKG 9.9 MW projects.
-tabMake Record Documents Maintenance Machinery Machinery Truck the machinery is heavy total for Power Plant Biomass APKG 9.9 MW projects and Inspect data of equipment Machinery total prepare procedure for Maintenance system and check preventive Maintenance for work.
-tabCheck lube oil, hydraulic oil Engine oil Skid installation Machinery And Truck the machinery is heavy Maintenance Work.
-tab Control Store Warehouses Construction company In Site Project Biomass APKG. 9.9 MW projects
-tabControl Sub- contractor and worker Installation Mechanical. And and electricity make diary Report
-tabCommand Working Construction Manager In Site Project Biomass APKG. 9.9 MW projects
From : October 2012 to December 2013
Company Name: Secco Engineering & Constrution Company. (Central Fastival Hatyai Project.)
Position: Foreman Technical Mechanical.
Job Detail : Planning and Control Vander Install Schedule for Mechanical Sanitary Work Group Total for Building
Central Fastival Hatyai Project.
Control Sub- contractor and worker installation Mechanical. About Air condition ,FCU ,AHU, chilled , sleeve
Block, SpringerPipe, Rain leader. , LPG System. Fire protection System And Main water pipe at Work. Central Fastival Hatyai
Project.
Commissioning run test Mechanical Sanitary Work Group and respontsiblelity defect work total all.
Central Fastival Hatyai Project
Prepare inspection sheet for Record Documents Daily Report and Request Work. Inspection work Send to
Consultants Adviser Project.
From : January 2014 To September 2016 (The Project Hatyai Municipal Waste Power Plant)
Company Name:Gidec Waste Power Plant Company .
Position: Oparation & Maintenances (O&M) (Project Hatyai Municipal Waste Power Plant)
Job Detail : Control Installation Machinery Line Process And Start Stop and Run Tests Commissioning.
Control And Field operator Monitor Line Process and Commissioning run test Start Up Stem Turbine and
Generators. preventive Maintenance Motor Bering Gear and Gear motor Turbine total.
Check pressure Compressors air Diary Weekly(Affa Copco Brand) And Check (PM) Pumping Cooling Tower
pressure Water 1 ,2 Line .
Check Lube oil Hydraulic Motor Gear Pump Control Machinery Auto and Manual.
and Check pressure Flow Stem 40 bar Turbine(Trivini Brand) and Generator Load .
Work Group and respontsiblelity Diary Report Everyday work total all.
Control Sub- contractor worker Mechanical. and electrical installation Machinery.
ประวัติการฝึกอบรม
มีนาคม 2550 ถึง มีนาคม 2550
วิยาลัยเทคนิคหาดใหญ่
การจัดการดรงไฟฟ้าจะนะ สงขลา
มีนาคม 2559 ถึง มีนาคม 2559
บ .ทรานย์ไทยมาเลเซีย ประเทศไทยจำกัด
การขับรถโฟล์คลิฟอย่างปลอดภัย
สิงหาคม 2559 ถึง สิงหาคม 2559
บ .ทรานย์ไทยมาเลเซีย ประเทศไทยจำกัด
การทำงานในที่อับอากาศ
ความสามารถ
ความสามารถทางภาษา
พูด (พอใช้) อ่าน (พอใช้) เขียน (พอใช้)
พูด (พอใช้) อ่าน (พอใช้) เขียน (พอใช้)
พูด (พอใช้) อ่าน (พอใช้) เขียน (พอใช้)
ไทย 25-30 คำ/นาที อังกฤษ 20-25 คำ/นาที
รถยนต์ ,รถจักรยานยนต์ ,
รถจักรยานยนต์ ,
Knowledge Of Tools Power tools. Hand Tools Specail Tools Genaral Tools. Machinery mechanical and electricity.
Basic About Computer Programmable Logic Control System(PLC)and Control System.
Knowledge Work About System Transmission, And Lubricant . Of Maintenance and Machine Automobile. Skill mechanical system And electric Basic.
Basic About Hydraulic Pneumatic System and mechanic Maintenance Work .
Good Work of Cooperative And To be Responsible.
Basic About Program Auto CAD ,Visio and Festo Program Other.
Skill read and Understand shop Drawing for construction work Mechanical Sanitary Work System .
Skill read and Understand (P&ID) Programmable Instruments Diagram
Able can skyscraper Work. Able can Hand work.. Able can Forklift.
Other Special Skills Language English : Speak Fair , Read Good ,Write Fair.
Driving Skill : Car Motorcycle .
โครงการ / ผลงาน / เกียรติประวัติ / บุคคลอ้างอิง
Seminars HISTORY
From : March, 2010
Seminars Course : Chana Power Plant and Management .
Seminars Institute: Hatyai Technical College and The Electricity Generating Authority Of Thailand (EGAT) .