Project management, Project coordinator, Automotive Sale
25,000บาท ขึ้นไป
10 ก.ค. 2562
6 ส.ค. 2562
ตำแหน่งที่สนใจ
Project management, Project coordinator, Automotive Sale
ประวัติการศึกษาสูงสุด
จบการศึกษาแล้ว ในปี พศ. 2559
ปริญญาตรี Sirindhorn International Institute of Technology - SIIT
Bachelor Degree
Civil Engineering
2.22
มัธยมศึกษาต้น-ปลาย Bangkok Christian Collage
High School
science-mathematics
3.33
ประวัติการทำงาน
3 ปี
สิงหาคม 2561 ถึง มิถุนายน 2562
Site Engineer Civil
Bouygues-Thai
489 Bond Street Road Bangpood, Pakkred Nonthaburi 11120
สำหรับสมาชิกเท่านั้น
[Project: Nimit Langsuan and Estelle sale gallery]
- Respond all civil work at ground floor and landscape.
- Issuing three week report and planning.
- Manage all material, machine, manpower and time.
- Provide daily report and request for manager and consult.
- Control all construction process.
[Project:Monorail Pink Line khae rai- min buri]
Office Engineer (OE)
-Verify the daily reports and daily requests from site works then delivers the documents to the consultant.
-Breakdown the construction and architecture plans to estimate the cost to set the budget, assign the work and do the cross checking.
-Issuing the Extension of Time (EoT) documents.
-Making the monthly progress to find the allowance by doing on-site estimation.
-Issuing the Colour Progress documents.(presenting the monthly progress by pictures)
-Making the Forecast Progress.
-Do the cost estimation of the invoice from the Sub-Contractor.
[Project: Fine Arts Department Office Building]
- Been responsible covered all of structure process since Foundation to Deck Floors.
- Inspect a sub-contractor works base on the theory of engineering and requirement of consultants or owner.
- Manage the construction plans to control construction time to correspond with the master plan.
- Estimate materials for the purchase requirement.
- Did the documents for the work permit and other requests including the payment of sub-contractors.
- Check some basic RC-design when changing shop drawing.
- Experienced in Post-Tension (Bonded system), Bored Pile (Wet process), Retaining system for deep excavations (Sheet Pile) and Form-work system.