SOME PROFESSIONAL PRACTICES:
2018 2019 Civil Engineer , 3B CABLE Co., Ltd.
PRARAM 3/2 PROJECT by Sinohydro Thailand Co.,Ltd.
Total Unit 490 Meters The Conversion Of Overhead
Total Cost 7.64 MB. Line To Underground System
MEDIUM VOLTAGE FOR MH.MRT02
MH.MRT06 , MH.MRT08 , MH.MRT10
MH.MRT12 4/HDD HDPE Ø160 mm.
CHIMPHLI, TALING CHAN PROJECT by Italian-Thai Development Public Co Ltd.
Total Unit 290 Meters The Conversion Of Overhead
Total Cost 15.93 MB. Line To Underground System
MH.13 TO MH.14
24/HDD HDPE Ø180 mm.
NFPT PROJECT by STREGA Pub Co., Ltd.
Total Unit 1,410 Meters The Fuel Pipeline Transportation
Total Cost 7.05 MB. Underground pipe Horizontal Directional Drilling
KP.157+673 To 158+625 at Nakhon Sawan
KP.302+399 To 302+485 at Kamphaeng Phet
CHIANG ROI YAI PROJECT by SIAM PATHUM GROUP Co., Ltd.
Total Unit 1 Units The Layout of new plumbing
Total Cost 2.43 MB. Underground pipe Horizontal Directional Drilling
Located at Chiang Roi Yai
Pathumthani
NAVANAKORN INDUSTRIAL ZONE PROJECT by ALT Telecom Public Company Limited
Total Unit 1 Units The Conversion Of Overhead
Total Cost 85 MB. Line To Underground Cable System
Located at Navanakorn Industrial Zone
Pathumthani
2016 2018 Civil Engineer , W.R.C. Electric And Communication Co., Ltd.
CONDO Q CHIDLOM PROJECT by Metropolitan Electricity Authority
Total Unit 1 Units The Conversion Of Overhead
Total Cost 1.3 MB. Line To Underground Cable System
Located at CONDO Q CHIDLOM
Bangkok
JITRADA PROJECT by Metropolitan Electricity Authority
Total Road 1 Road The Conversion Of Overhead
Total Cost 15 MB. Line To Underground Cable System
Located at Phitsanulok Road
Bangkok
PIPE JACKING PROJECT by Metropolitan Electricity Authority
Total Manhole 56 Manhole Construction of Reinforced Concrete
Total Cost 30 MB. Pits For Pipe Jacking Works
Located at Naradhiwas Rajanagarindra Road
Bangkok
NAWAMIN PROJECT by Metropolitan Electricity Authority
Total Meter 1230 meter Underground Duct Bank And Manhole
Total Cost 15 MB. Of Horizontal directional Drilling Works
Located at Nawamin Road
Bangkok
.
NONSEE PROJECT by Metropolitan Electricity Authority
Total Road 7 Road The Conversion Of Overhead
Total Cost 139 MB. Line To Underground Cable System
Located at Narathiwatratchanakarin Road
Nang Lin Jee Road , Sathupradit Road
Ratchadaphisek Road , Anuman Rajdhon Road
Sawang arom Road , Sathorn Road
Bangkok
CHITRALADA PROJECT by Metropolitan Electricity Authority
Total Meter 886 meter The Conversion Of Overhead
Total Cost 17 MB. Line To Underground Cable System
Located at Phetchaburi Road
Bangkok
PHAYATHAI PROJECT by Metropolitan Electricity Authority
Total Meter 1,361 meter The Conversion Of Overhead
Total Cost 30 MB. Line To Underground Cable System
Located at Ratchaprarop Road
Bangkok
2014 2016 Civil Engineer , Minerva Management Co., Ltd.
CHATEAU IN TOWN RAMA 8 by CMC Group
Total Unit 506 Units 13-Storeys 1-Building.
Total Cost 716 MB. Located at Rama 8 Road, Tambon
Bang Yi Khan, Bangplad, Bangkok
VILLA LASALLE by Origin Property
Total Unit 353 Units Located at C 18 La Salle, Sukhumvit Rd.,
HAPPY AVENUE DONMUANG by Infinite Real Estate
Total Unit 1 Units Avenue Building.
Total Cost 180 MB. Located at Song Prapha Road, Tambon
Donmuang, Muang, Bangkok.
HAPPY VILLE DONMUANG by Infinite Real Estate
Total Unit 342 Units Townhome Building.
Total Cost 630 MB. Located at Song Prapha Road, Tambon
Donmuang, Muang, Bangkok
DCONDO NOEN PHRA RAYONG by Sansiri
Total Unit 328 Units 8-Storeys 2-Building.
Total Cost 183 MB. Located at Sukhumvit Road, Tambon
Noen Phra, Muang, Rayong
DCONDO NAKORN RAYONG by Sansiri
Total Unit 575 Units 8-Storeys 3-Building.
Total Cost 372 MB. Located at Sukhumvit Road, Tambon
Noen Phra, Muang, Rayong