Responsibility 2 factory; 4 part
1. Project part; Responsibility 2 factory
- Coordinate Contractors.
- PR and coordinate with purchasing process.
- Design parts and machinery.
- Production process control parts.
- Inspect material follow engineer designer.
- Control installation machinery and equipment, Machine of extrude line, Machine of heat exchanger and pump system, Machine of LPG bulk gas to piping supply system, Machine of coal Boiler 8Mcal/hr. and Piping Thermal hot oil supply-return system, Machine of chiller water cooling and piping system, Machine of air compressor and piping system, Tank compound and piping system, Building all, Foundation all.
- Commissioning machinery after Installation completed.
2. R&D part; Responsibility 2 factory
- Research and development of machinery.
- Research and development team of process manufacturing.
- Find solution for increased output of productivity and process of manufacturing.
3. Energy Management part; Responsibility 2 factory
- Research and development solution of energy saving, electric energy and heating energy.
- Energy management, 8 steps
- Internal audit of annual energy management.
- External audit of annual energy management.
- Follow up schedule of annual energy management from DOE.
4. Drawing part; Responsibility 2 factory
- Setting draftsman make to drawing follow engineer design.
- Setting standard of drawing.
- Setting drawing number match part of maintenance team.
- Make to drawing list system for find big data support Maintenance team.
Other ; Responsibility 2 factory
- Carbon footprint. (CFO)
- Follow up management policy for plan to expand capacity to grow for the factory.
- Plan strategic sent to top management.
- Manage in engineering department.
- Arrangement and setting KPI in department.
- Contact the relevant authorities.
- Annual Inspection of 2 Coal fuel Boiler 8 Mcal/hr.
- Annual Inspection of 2 Oil fuel Boiler 1.5 Mcal/hr.
- Annual Inspection of 2 Oil fuel Boiler 2.5 Mcal/hr.
- Annual Inspection of 2 Oil fuel Boiler 3 Mcal/hr.
- Management, Responsible for supervising, coordinating and directing design work, installation work, inspection work.
- Comparison BOQ.
- Prepare and control schedule plan and material in time.
- Meeting emergency plan and joined emergency with all department.
- Control the budget.
- Arrangement document for support audit. (ISO 9001)
- Contact the relevant authorities.
- Coordinate Contractors.
- PR and coordinate with Purchasing Process.
- Design parts and Machinery
- Production process control parts.
- Control installation Machinery and Equipment, Machine of Glove Dipping Line, Machine of Wastewater Treatment, Machine of Ro water system, Machine of Fire pump system, Machine of LPG Bulk gas to piping supply system, Machine of Gas Boiler 10ton system and Piping Thermal hot oil supply-return system, Machine of Chiller air cooling and Piping system, Machine of Air Compressor and Piping system, Machine of Overhead Crane 2ton, Machine of Scrubber system, Piping manifold of Chlorine system, Tank compound and Piping system, lighting system, Air conditioner, Building all, Foundation all, MDB SDB DB system.
- Plan of operations, Gas Boiler Hot Oil 10ton, Chiller air cooling system, Air Compressor system, Ro water system, LPG Bulk gas supply system.
- Research and development of Machinery
- Management, Responsible for supervising, coordinating and directing design work, installation work, inspection work, permission work, document work with a value of more than 300,500,000 baht.
- Prepare Material and Plan Manpower for Maintenance Job, Operation Job, Project Job.
- Meeting emergency plan and joined emergency with all department.
- Spare equipment and parts.
- Control the budget.
- Arrangement and setting KPI.
- Arrangement Document for Audit (ISO 9001, 13485, 14001, 45001), OHSAS 18001, SMETA Audit.
ไม่ได้ระบุ
Manager site Engineer
Sotus Engineering
2248 Punnakan Road, Kho Hong Subdistrict, Hat Yai District, Songkhla 90110
สำหรับสมาชิกเท่านั้น
Type of work:
- Research and development of Machinery
- Design parts and Machinery
- Production process control parts.
- Control installation Machinery and Equipment. Blower, Water feed Pump, Piping system,
Turbine Condenser Generator, Structure
Support, Chain conveyor
- Plan of Operations.
- Contact the relevant authorities.
- Sales service
- Sales management
- Arrangement Document for client open
Quotation and PO
- Prepare Material and Plan Manpower for project.
- Follow Invoiced from client.
- Meeting emergency plan and joined emergency with customer. - Purchase equipment parts - Vibration analysis Blower, Pump, Bearing - Alignment Blower, Pump - Field balance, Blower, Pump, Shredder - Survey camera - Control the budget.
2016–2018 A.G.Precesion Part., Ltd.
Position: Sale Engineer & Manager
Type of work:
- Research and development of Machinery
- Design parts and Machinery
- Production process control parts.
- Control install Machinery and Equipment.
- Plan of Operations.
- Control the budget.
- Contact the relevant authorities.
- Sales service
- Sales management
- Arrangement Document for client open PR/PO
- Prepare Material and Plan Manpower for project.
- Follow Invoiced from client.
- Meeting emergency plan and joined emergency with customer.
-Purchase equipment parts
2013–2016 Prince of Songkla University
Position: Researcher
Type of work:
- Research and development of Heat Transfer
- Publish academic articles
- Design parts and accessories of Industrial machinery that Heat Transfer
- Prepare Material and Plan Manpower for project.
- Install Machinery and Equipment that Heat Transfer
2010–2013 Siam Sempermed Corp , Ltd , Company
Position: Line Maintenance Engineer (R&D, MI)
Type of work:
- Design Machine and accessories parts of machine,
Cleaning brush, Pre-cuff, Brush Roll edge, Powder tank
Striping sucker
- Control. Parts and accessories.
- Control and Installation updates. Machinery Line 1-84 - Control Installation equipment.prototype the former double glove production line 81-84
- Plan of operations maintenance.
- Control the budget.
- Contact the relevant authorities. - Purchase equipment parts list.
Using The program Simulation Fluent., Using The program Drawing Solidwork.
ความสามารถ
ความสามารถทางภาษา
พูด (ดีมาก) อ่าน (ดีมาก) เขียน (ดีมาก)
พูด (พอใช้) อ่าน (ดี) เขียน (ดี)
ไทย 35 คำ/นาที อังกฤษ 30 คำ/นาที
รถยนต์ ,
รถยนต์ ,
สามารถใช้โปรแกม Word , Excel , Power Point, Autocad2D, Solid Work(simulation), Fluent, Internet, E-mail, Calculate, Analyze, Financial
โครงการ / ผลงาน / เกียรติประวัติ / บุคคลอ้างอิง
2024 Natural rubber thread Co.,Ltd, Branch 2, Increased output of productivity and process of manufacturing.
2023 Natural rubber thread Co.,Ltd, Branch 1, Report of Energy management 2023 follow DOE.
2023 Natural rubber thread Co.,Ltd, Branch 2, Report of Energy management 2023 follow DOE.
2023 Natural rubber thread Co.,Ltd, Branch 1, Report of Carbon footprint. (CFO) 2023.
2023 Natural rubber thread Co.,Ltd, Branch 2, Report of Carbon footprint. (CFO) 2023.
2023 Innolatex (thailand) Ltd, Condom Factory, Documents certifying the renewal of business operations from the IEAT.
2022 Innolatex (thailand) Ltd, Glove Factory, Documents certifying the Business commencement from IEAT.
2022 Innolatex (thailand) Ltd, Glove Factory, Permit to notify Business commencement from IEAT.
2022 Innolatex (thailand) Ltd, Glove Factory, Documents certifying the Installation Machine from IEAT.
2022 Innolatex (thailand) Ltd, Glove Factory, Permit Testing of Machine from IEAT.
2022 Innolatex (thailand) Ltd, Glove Factory, Permit to Store and using flammable substances (LPG) from Department Of Energy.
2022 Innolatex (thailand) Ltd, Glove Factory, Apply for permit to deposit and using controlled Chlorine gas from Regiment of the Military.
2022 Innolatex (thailand) Ltd, Glove Factory, Permit to install Electricity Transformer from PEA and Documents certifying the Installation Electricity from PEA.
2022 Innolatex (thailand) Ltd, Glove Factory, Documents certifying the Installation of factory Layout, Building Construction, Installation Machinery, Installation Low and High Voltage Electricity, Installation Dustcollector and Installation Wastewater Treatment systems by Profesional Engineers and Profesional Architecture signed approved (Field, Engineer of Industrial, Engineer of Civil, Engineer of Mechanical, Engineer of Electrical, Engineer of Eenvironment, Architecture).
2022 Innolatex (thailand) Ltd, Glove Factory, Cordinate with IEAT, Documents of Building, Documents of Machinery, Documents of Electrical systems, Documents of Dustcollector and Documents of Wastewater Treatment systems.
2021 Innolatex (thailand) Ltd, Glove Factory, Building certification from IEAT
2021 Innolatex (thailand) Ltd, Glove Factory, Permit of additional the building and modify the building from IEAT
2021 Innolatex (thailand) Ltd, Glove Factory, Controller the job Installation of Machine, Machine of Glove Dipping Line, Machine of Wastewater Treatment, Machine of Ro water system, Machine of Fire pump system, Machine of LPG Bulk gas to piping supply system, Machine of Gas Boiler 10ton system and Piping Thermal hot oil supply-return system, Machine of Chiller air cooling and Piping system, Machine of Air Compressor and Piping system, Machine of Over head Crane 2ton, Machine of Scrubber system, Piping manifold of Chlorine system, Tank compound and Piping system, lighting system, Air conditioner, Building all, Foundation all, MDB SDB DB system.
2021 Site Manager location in Nakhon Sawan, GGC KTIS Bio Industrial Company Limited (GKBI) Responsible for installation of Shin nippon Steam turbine 38Mw. 2Ea and Shin nippon Steam turbine 9Mw. 1Ea, Alignment Pump Blower Mortor
2021 Project Engineer location in Khon kaen, Advance Asia Power Plant Co., Ltd. 9.9 Mw.(ACE Group). Responsible for Major Overhaul Hangzhou Steam turbine 7.5Mw.
2021 Project Engineer location in Trang, Pitak Palm Oil Company Limited. Responsible for Installation and Modify Line Conveyor to Sling (R&D) (Save cost maintenance, Save cost spare part, Save cost stock part, Save breakdown, Save cost preventive maintenance, Save cost manpower, Save manpower, Save loss time, Increase production capacity)
2020 Project Engineer location in Surat Thani, Sangsiri Agro Industry Company Limited. Responsible for Major Overhaul Skoda Jinma Steam turbine 7.5Mw.
2020 Project site location in Krabi Province, Absolute Clean Energy Public Company Limited (ACE Group) Power plant 6Mw. Responsible for installation of pipe support, Piping system all line steam, Hangzhou Steam turbine 6Mw. condensor generator, Vibration analysis, Alignment ID fan.
2016 Conference of Mechanical Engineering Network of Chiang
mai University
2015 The 29th Conference of Mechanical Engineering Network of
Thailand
2011 – 2013 Instructor Training in Siam Sempermed Corp , Ltd ,
Company ( Bearing).
The Labor Committee in Siam Sempermed Corp , Ltd Company
2012 Top 2 QCC SritrangGroup Corp, Ltd, Company.
Top 1 QCC Siam Sempermed Corp, Ltd, Company
Top 8 KAIZEN Siam Sempermed Corp, Ltd, Company
2011 Top 3 QCC SritrangGroup Corp, Ltd, Company.
Top 2 QCC Siam Sempermed Corp, Ltd, Company
Top 1 KAIZEN Siam Sempermed Corp, Ltd, Compan
2009 Second Class Honours (Mahanakorn University).
Study of heat transfer of air. The distance between the conical ring surface.